Application for approval of regulator for proposed Class 1 or 2 demolition work not in accordance with standard (1)

A person who proposes to carry out Class 1 demolition work or Class 2 demolition work but to carry out the work in a manner that would not be in accordance with AS 2601 must, at least 10 working days before the work is intended to begin, apply to the regulator for approval to carry out the work.