The principal contractor for a construction project must put in place arrangements for ensuring compliance at the workplace with the following — (a) Part 3.2 Division 2; (b) Part 3.2 Division 3; (c) Part 3.2 Division 4; (d) Part 3.2 Division 5; (e) Part 3.2 Division 7; (f) Part 3.2 Division 8; (g) Part 3.2…
The principal contractor for a construction project must put in place arrangements for ensuring compliance at the workplace with the following — (a) Part 3.2 Division 2; (b) Part 3.2 Division 3; (c) Part 3.2 Division 4; (d) Part 3.2 Division 5; (e) Part 3.2 Division 7; (f) Part 3.2 Division 8; (g) Part 3.2…
The principal contractor for a construction project must in accordance with Part 3.1 manage risks to health and safety associated with the following — (a) the storage, movement and disposal of construction materials and waste at the workplace; (b) the storage at the workplace of plant that is not in use; (c) traffic in the…
The principal contractor for a construction project must in accordance with Part 3.1 manage risks to health and safety associated with the following — (a) the storage, movement and disposal of construction materials and waste at the workplace; (b) the storage at the workplace of plant that is not in use; (c) traffic in the…
The principal contractor for a construction project must take all reasonable steps to obtain a copy of the safe work method statement relating to high risk construction work before the high risk construction work commences. Note for this regulation: The WHS management plan contains arrangements for cooperation between persons conducting a business or undertaking at…
The principal contractor for a construction project must take all reasonable steps to obtain a copy of the safe work method statement relating to high risk construction work before the high risk construction work commences. Note for this regulation: The WHS management plan contains arrangements for cooperation between persons conducting a business or undertaking at…
In this regulation — WHS management plan means the initial plan and all revised versions of the plan.
Subject to subregulation (2), the principal contractor for a construction project must ensure that a copy of the WHS management plan for the project is kept until the project to which it relates is completed.
If a notifiable incident occurs in connection with the construction project to which the statement relates, the person must keep the WHS management plan for at least 2 years after the incident occurs.